4 Site Planning
4.1 Site Selection Criteria
The following are guidelines for selecting the installation location of the 45 Mbps Backhaul ODU and PIDU.
4.1.1 ODU Site Selection
When selecting a site for the ODU the following should be taken into consideration:
That it is not possible for people to stand or walk inadvertently in front of the antenna.
Height and location to achieve the best radio path
Height in relation to other objects with regard to lightning strikes
Protection from the weather
Aesthetics and planning permission issues
Distance from PIDU and connected equipment (Maximum cable run ODU to connected
equipment is 328 ft (100m))
Distance from the PIDU to the ODU (Maximum cable run PIDU to ODU is 328 ft (100m))
4.1.2 PIDU Site Selection
When selecting a site for the PIDU the following should be taken into consideration:
Availability of a mains electricity supply
Accessibility for viewing status indicators and pressing reset switch (See section 1.3.2 “The
Power Indoor Unit (PIDU)” and section 7 “Fault Finding”
Distance from ODU and connected equipment (Maximum cable run ODU to connected
equipment is 328 ft (100m))
Distance from the ODU to the PIDU (Maximum cable run ODU to PIDU is 328 ft (100m))