March 2005 Building Your Canopy Network
Through Software Release 6.1
Page 264 of 425 Issue 1
Canopy System User Guide
CAUTION!
Failure to perform the following step can result in damage to equipment.
5. Set the 115-/230-volt power switch in the CMM2 consistent with the power
source. See Figure 101.
115/230 V switch
AC power
connectors
Fuse receptacle
Figure 101: Location of 115-/230-volt switch
IMPORTANT!
The AC power connectors are labeled N for Neutral, L for Line, and PE
for Protective Earth (PE)
or ground. The maximum thickness of wire to
be used is 4 mm
2
or
12 AWG.
6. Route the Ethernet cables from the APs and or BHs to the CMM2.
The strain relief plugs on the CMM2 have precut holes. Each hole of the strain
relief is designed to hold two CAT 5 UTP cables or one shielded cable. The
Ethernet cables have RJ-45 (standard Ethernet) connectors that mate to
corresponding ports inside the CMM2.
These ports are labeled J3. Eight J3 ports are available on the CMM2 to
accommodate any combination of APs and BHs.