User's Manual

Mechanical Installation Process Chapter 1: Understanding the Installation Process
Process 1-1 Installing Hardware Components
1 Place each piece of equi
pment carefully in the area designated on the site plan.
2
Verify that the equipment rack is bolted to the floor and ready for equipment
installation.
See "Verifying Proper Installation of the Equipment Cabinet or Rack" on page
1-5.
If your system was racked and tested by Motorola CCSI, continue
with step 7.
3
Identify the rack space or Rack Unit (RU) location where the hardware
component is to be mounted.
An RU is the standard smallest rack panel height. Its standard
definition is 4.45 cm (1.75 in.).
4
Locate the hardware component near the rack.
Observe all safety
precautions when lifting heavy equipment. See
"Lifting STR 3000 Simulcast Base Radio Racks" on page 2-3 for
more information on these precautions.
5
Lift and slide the component into the rack.
See "Installing Equipment in the Equipment Cabinet or Rack" on page 1-6.
6 Attach the chass
is to the rack with the recommended type and size screws or bolts.
7
Verify that all boards are properly seated into the chassis, if applicable.
8
Cable the component to the system components.
For the installation of each component, see:
Chapter 3,"Ins
talling the Prime Site (10Base-2)."
Chapter 4,"Installing the Prime Site (10Base-T)."
Chapter 5,"Installing the Digital Simulcast Remote Site (10Base-2)."
Chapter 6,"Ins
talling the Digital Simulcast Remote Site (10Base-T)."
1-2 68P81003Y71-O November 2002