User's Manual Part 1

Simulcast Hardware Installation Site Preparation
Process 2-1 Installing Equipment within a Digital Simulcast Subsystem
1
Prepare each site to com
ply with the Motorola requirements and specifications
for the equipment, as listed in the Standards and Guidelines for Communication
Sites (68P81089E50) manual. Other codes and guidelines that may apply to
the location must also
be met.
2
Inspect and inventory all racks, cabinets, cables, and other equipment with a
Motorola representative to ensure that the order is complete.
3
Install all equipment using the site drawings and other documents provided by
the Field Engineer. Use the installation standards and guidelines for placing and
installing equipmen
t.
4
Install all groundings for the racks and cabinets to protect against ground faults,
electrical surges, and lightning in accordance with R56 standards..
5
Connect all cables within each rack and between multiple racks (where required).
Connect the subsystem to the overall facility system.
6
Run a preliminary check of all sites before applying power and starting the initial
software installations.
Site Preparation

PerformtheactivitieslistedinTable2-1toensure proper site preparation. The table
also references specific chapters in the Standards and Guidelines for Communication
Sites (68P81089E50) manual for more information.
68P81003Y71-O November 2002 2-7