Step 5 - Network Connections
Network connections allow the TriStar MPPT 600V to communicate with other controllers or com-
puters. A network can be as simple as one controller and one PC, or as complex as dozens of
controllers monitored via the internet. Review section 5.0 for more information about networking
and the connection(s) required for your system.
WARNING: Shock Hazard
Never route network cables in the same conduit as the power conductors.
WARNING: Shock Hazard
Only use 300 Volt UL rated communication cable.
AVERTISSEMENT: Risque de décharge électrique
N’acheminez jamais les câbles réseau dans le même conduit que les conducteurs
d’alimentation.
AVERTISSEMENT : Risque de décharge électrique
N’utilisez qu’un câble de communication 300 V homologué UL.
Connect the appropriate network cables to the TriStar MPPT 600V at this time. Access to the
network ports is easier before the battery power cables are attached. The ports are located inside
theconduitwiringboxonthelowercircuitboardasshowningure3-12.
EIA-485 (4 - position)
RJ-45 Ethernet
RJ-11 MeterBus
TM
RS-232 (9 - pin female)
Figure 3-12. TriStar MPPT network port locations
EIA-485 Connection
The four (4) position EIA-485 connector on the TriStar MPPT must be removed to access the
terminalscrews.Removethesocketconnectorbyrmlygraspingtheconnectorbodyandpulling
awayfromthecircuitboardasshowningure3-13.