Step 4: Accessories (optional)
Install the Remote Temperature Sensor and Remote
Meter (both purchased separately) if required. Refer to
the instructions provided with each accessory for detailed
installation procedures.
Step 5: Conrm Wiring
Double-check the wiring in steps 1 through 4. Conrm
correct polarity at each connection. Verify that all seven (7)
SS-MPPT power terminals are tightened.
Figure 7. System Wiring Review
+
-
2
1
3
Step 6: Install Fuses
Install a 25 Amp DC-rated fuse in each fuse holder in the
following order:
1. Load circuit
2. Battery circuit
Step 7: Conrm Power-up
The SS-MPPT should begin the power-up LED sequence
when battery power is applied. Observe that the Battery
Status LEDs blink in sequence one time.
If the SS- MPPT does not power up or a ashing LED
error sequence exists, refer to Section 6.0 Troubleshooting.