Installation
Direct Vent Installation
Vent systems that terminate through a wall may comprise up to six
different components:
A - Termination PTO-3 (3" length)
PTO-3F (3" length)
B - Stucco Kits MSR (stucco frame)
MOSR (stucco can)
BSR (brick can)
C - Flex sections PFL-1 (12" section)
PFL-2 (24" section)
PFL-3 (36" section)
PFL-4 (48" section)
D - Solid sections PEXT-1 (12" section)
PEXT-2 (24" section)
PEXT-3 (36" section)
PEXT-4 (48" section)
E - Extensions PXT-5 (5" section)
PXT-10 (10" section)
F - 90° elbow PEL-90F/F
PEL-90M/M
Short Configurations:
For installations straight through the wall, use a 2" or 5" termination
(see above chart for Part #), and PXT-5 or PXT-10 to achieve the
desired length. The maximum horizontal vent run with no vertical lift is
12".
See Figure 7.
Example:
A rigid section and an elbow used in conjunction with 3 ft. flex section
(PFL-3) will, when extended in a chase, allow for a maximum horizontal
run of twelve and one-half feet from the centre of the fireplace to
outside wall and a minimum of 7'6" when retracted in opposite
direction. (See Figure 8 and 9.)
"C" flex sections and "D" solid sections may be used in conjunction with
one another to obtain different possible horizontal length installations.
NOTE: Flex section must not exceed maximum horizontal length of 3
feet.
Long Vent Runs:
For longer or more complex vent runs, vertical lift is required. First
ensure that the planned run is acceptable using the Vent Graph. Plan
out the required components using the chart above. You may be able
to use fewer components using the chart below.
Figure 7. Short Horizontal installation with PEL90-FF elbow.
Figure 8. Extended installation.
Figure 9. Retracted installation.