Owner`s manual
XG0147 - 011912.1
Installation
6”
When installing a shelf over the top of the replaces, the following
guidelines must be adhered to:
For Rear Vent applications, the minimum clearance is 2" from the rear
of the replace to a wall, or any combustible materials, and 9" clearance
from the top of the replace to the underside of any combustible shelf
materials.
For Top Vent applications, the minimum clearance is 2" from the rear of
the replace to a wall, or any combustible materials, and 17 1/2" to the
underside of any combustible shelf materials, Figure 4.
For Top or Rear Vent applications where the Minimum mantel height
is required above the replace, (for an alcove or low prole shelf), ALL
Materials , Figure 5. The minimum
clearance is 2" from the rear of the replace to a wall, or any combustible
materials.
1” clearance is maintained on sides and bottom of vent runs and 2”
above horizontal vent runs to any combustible material.
The replace clearances are shown below:
†
The replace is supplied with two standoffs. Bend and install these
standoffs on top of the replace ensuring that the height of the standoff
maintains a 6" clearance.
Installing the standoff's.
Installing the Nailing Flange Extension.
Once the replace is placed into the rough framed opening, the supplied
Nailing Flange Extention(Part No. ) must be fasten securely into
place, with nails or wood screws. as shown in Figure 7.
The nailing ange extension can be substituted with a piece of
material of the same size and thermal characteristics,
ie: cement board or equivalent. This is recommended in applications
where the facing materials will not adhere to the metal nailing ange.