Owner`s manual
H*38DF PRC Panorama Indoor Gas Fireplace
Page 7
XG0211 - 040912.1
Installation
Clearances
When installing a shelf over the top of the replaces, the following
guidelines must be adhered to:
For Rear Vent applications, the minimum clearance is 1" from the rear of
the replace to a wall, or any combustible materials, and 11" clearance
from the top of the replace to the underside of any combustible shelf
materials.
For Top Vent applications, the minimum clearance is 1" from the rear of
the replace to a wall, or any combustible materials, and 17 1/2" to the
underside of any combustible shelf materials.
1” clearance is maintained on sides and bottom of vent runs and 2”
above horizontal vent runs to any combustible material.
MODEL
Top -
Rear Vent
†
Top -
Top Vent
†
Header
Sides
Front
Rear
Venting - Top
Venting - Sides,
bottom
H*38PR* 11" 17 1/2" 4" 0" 0" 1" 2" 1"
Installing The Standoffs
To avoid elevated mantel temperatures, all H*38PR* gas
replaces are required to have the supplied standoffs installed.
The replace is supplied with two standoffs. Bend and install these
standoffs on top of the replace ensuring that the height of the standoff
maintains a 8" clearance.
Figure 6. Installing the H*38PR* standoffs.
† Note: Clearance from top of replace to a combustible ceiling within
the replace enclosure.
Fasten Standoffs
in gutter
8”
Nailing Flange Extension
The 4" nailing ange extension is shipped attached to the top edge of
the replace, see Figure 1.
The nailing ange extension may be substituted with a piece of NON-
Combustible material of the same thermal characteristics, ie: cement
board or equivalent to t the opening. This is recommended in applications
where the facing materials will not adhere to the metal nailing ange.
To remove the Nailing Flange Extension follow the directions below:
Figure 7c. Finished removing Nailing Flange extension.
Figure 7. Remove screws from top of the unit
Figure 7a. Remove shell from the top of unit. Remove screws from outer edge.
Figure 7b. Remove the nailing ange extension from the unit. Reinstall shell.
Screw shell in place.