STEP 1 CONTINUED
• Arrange cross-framing in the ceiling to suit the existing
structure. See examples.
– Secure each 2 x 4 block with at least four (4) #10 wood
screws, 3" long (not supplied). Use 8 wood screws total
for the two supports.
The cross-framing must be accurately aligned to
ensure correct positioning of the hood.
The cross-framing must be level in all directions.
Check with a spirit level and adjust if necessary.
IMPORTANT: The ceiling structure must be capable of sup-
porting the weight of the hood (approximately 300 pounds)
and any inadvertent user contact loads. The hood support
frame will be supported by the 2 x 4 min. cross-framing.
Ductwork
Use the shortest and straightest duct route possible. For
satisfactory performance, duct run should not exceed
100-feet equivalent length for any duct conguration.
Refer to “Duct Fittings” chart to compute the maximum
permissible length for duct runs to the outdoors.
This vent hood must use 8" round duct. The 8" round
duct can transition to 3-1/4" x 12".
Install the house ductwork to run horizontally between
ceiling joists or straight up through the roof.
Finish the Ceiling
Finish the ceiling surface. Be sure to mark location of
the ceiling joists and cross-framing. Check to be sure
the ceiling is level; use shims, if necessary.