Instructions / Assembly

866.729.2378 | WWW.MOISTURESHIELD.COM
Lay a top and bottom magnum rail along the edges of the steps and up next
to the post.
A. Position both rails for marking with the 2-5/8-inch leg lying on the steps.
B. Mark the rails on the inside faces of the two upright posts.
C. Cut each rail along this mark (line).
Position bottom magnum rail 1/2-
inch above edges of steps (check
local code) support on blocks cut
from scrap material.
Cut ends of two balusters at
the same angle as the top and
bottom magnum rails and use
them as the post balusters.
To complete stair railing follow steps #1B
through #7 from the composite railing
installation section.
3.
4.
5.
6.
72"