Installation Instructions

PERFECT
SEAL
PerfectSeal
Installation Guide
Waterproof Laminate Flooring
This document is reviewed on an ongoing basis.
SV_0878 7/20
Site and Material Preparation
E
suboor
subsuelo
> 8" (200 mm)
6 mil (0.15 mm) virgin
polyethelene vapor barrier
Barrera de vapor de 6 mil
(0,15 mm) de polietileno virgen
F
G
%
48 hours
48 horas
60° – 85° F
15°C à 29°C
35% – 65% RH
35% à 65% HR
D
CA
Door Frame
Marco interior de
la puerta
Wallbase
Zócalo
Casing
Marco
1 inch
(2,5 cm)
B
Cutting Line
Línea de corte
A. Remove carpet and padding. Also remove any wood ooring installed on concrete. Do not remove products unless they are
asbestos-free.
B. Undercut door frame and wallbase. Slide the ooring at least 1/4" underneath the door frame and wallbase. Also leave a
concealed 3/8" minimum expansion space under each.
C. Remove bumps or peaks in suboor and ll depressions with oor leveling compound to ensure no more than 3/16"
unevenness per 10-foot span.
D. Acclimate unopened product before installation. If there is no time for acclimation, there should be no more than a difference
of 25° F and 20% relative humidity between the stocking/transportation environment of the ooring and the nal installation
environment of the ooring.
E. Clean debris from suboor before installation.
F. For concrete suboors, install vapor barrier with overlapped seams of 8" or more.
G. For planks without attached underlayment, install over single layer of underlayment appropriate for laminate oors.
3