Installation Guide

©2016 Aladdin Commercial
|
www.aladdin-commercial.com
|
1-800-2MOHAWK©2016 Aladdin Commercial
|
www.aladdin-commercial.com
|
1-800-2MOHAWK
Required Equipment
Thefollowingitemsmaybepurchasedfromalocalcarpetworkroomsupplier:
• RazorBlades•RazorKnives
StraightEdge•Chalkline
MohawkGroup’sAdhesives•Scissors
FramingSquare•FloorScraper
CushionBackCutter•75lb.Rolleror100lb.Roller
TapeMeasure  •PortlandPatchingCompound
 •HeavyDutyFramePaintRollerwith3/8”NapRollerora1/16”x1/32”x1/32”U-notchtrowel
Floor Priming
Concrete:Primeifoorisextremelyporousorhasexcessivedust.Note:Anyexistingsealerorprimer
mustbetestedforcompatibilitywithMohawkadhesives.Terrazzo,Marble,VinylTile(VATorVCT),Lino-
leumandothersmoothnonporoussurfacesdonotrequirepriming.Dampmoponly,ifpatchingisrequired
ontheseareas,primethepatchedareasifrequiredbypatchmanufacture.
NOTE: When non-asbestos containing cut-back or any incompatible adhesive is present, existing
adhesive has evidence of plasticizer migration, or UltraSet (PVC) products are being installed, the
existing adhesive must be properly removed and Mohawk OptiSeal must be applied over the
adhesive residue. Chemical adhesive removers cannot be used to remove old existing adhesives.
Plywood Floors:PlywoodFloorsmustbecompletelyprimed.Plywoodsubstratesmustbenolessthan
3/4”thickness.Particleboardorthinplywoodisnotanacceptablesubstrate.
Site Layout
1.Thestartingpointinamodularinstallationmustbeasneartothecenteroftheroomaspossible
andmustbepositionedtoutilizethelargestperimetercutmodulesize.
2.Snapachalklineparalleltoonemajorwallbisectingthestartingpoint.Itwillbenecessarytooffset
thecenterchalklinetoassureperimetermoduleswillbeatleasthalfsize.
3.Asecondchalklinemustbesnappedfromthestartingpointat90°totherstline.Thiscanbe
accomplishedusinga6-8-10,orlargertriangle,dependingontheroomsize.(Seebelow)Metersorfeet
willbeusedtolieoutthetriangleintheseproportions.Framingsquarecanalsobeused.
A bond test must be performed over concrete substrates with unidentied sealers or primers:
Adhere a small area of 2-3 feet of carpet and allow it to dry completely. Let it set for 24 hours.
If the adhesive is bonded tightly, proceed with installation.
Pallet and Box Sequencing
It is very important to install carpet tiles in the order they
were manufactured. This is easily accomplished by selecting pallets in sequential order.
10’ 6’
8’