2 BEEKs and BluFi installation
1. BluFi installation
1. BluFi should be installed within 100ft (30m) of monitored
assets (shorter distances required for environments with
obstructions).
3. Surface preparation
1. Ensure the asset installation surface is clean and free
of oil, dirt, rust, and paint chips and the beacon is not
covered by metal to ensure good radio transmission.
2. Beacons should be mounted to a clean, flat, rigid surface
of the asset to be monitored. For vibration monitoring
with BEEKS001-CM, the mounting should be close to the
source of vibration. The beacon should be oriented such
that its three axes are parallel to the three axes of the
asset.
4. Policy creation
Now you are ready to use the beacon for your use case.
Start creating policies as decribed in our on-line manual
hid.gl/On-line-manual
4. BEEKs installation
1. Standard beacons may simply be mounted by using the
integrated peel-o sticker.
2. BEEKS001-CM requires special mounting with Epoxy
glue to ensure proper pick-up of the vibration data of the
underlying asset. We recommend Devcon 5-minute or
Loctite AA 330
3. Apply line of epoxy to bottom of beacon.
4. Place beacon and press firmly.
5. Wait five minutes and confirm beacon is secure.
2. BEEKs location
1. Place beacons near the desired assets (don’t install yet).
2. In Bluzone console, go to BluFi > {BluFi Name} >
Statistics and scroll down to the Scan Map.
3. Verify that each beacon sees at least one BluFi. (-75 dBm
or higher is desired). Move BluFi’s if necessary.
For more detailed information, visit https://hid.gl/HID-BEEKs-installation
AC BluFi Option
T
R
A
X
Z
Y
T
A
R
Orientation
A = Axial
R = Radial
T = Tangential
Vertical motor mount
Horizontal motor mount