User manual
INSTALLATION
8
INSTALLATION
ONTO A WALL
MILLDROP can be placed on a working plane, mounted on the Millrack system (see the
relating User Manual) or installed on a wall (see Fig. A-B-C). In this last case, proceed as
follows:
1. Remove the screws (1) and the lid (A). Figure A
2. Remove the screws (2-3) and the side panel (B). Figure A
3. Position the panel (B) on the wall where MILLDROP has to be installed and mark the
wall by a pencil in the mounting slots (C). Figure B
NOTE
T
HE DEMINERALIZER MUST BE INSTALLED PERFECTLY HORIZONTAL, OTHERWISE
THE ANTI
-FLOODING SYSTEM COULD NOT PROPERLY FUNCTION. ON CHOOSING
THE INSTALLATION POINT
, CONSIDER THE ROOM NECESSARY FOR REAR PIPING,
FOR THE FRONT PANEL FREE VISION AND FOR THE ADEQUATE VENTILATION
(SEE
PARAGRAPH
GENERAL INSTALLATION PRECAUTIONS).
4. Bore the holes corresponding the marks just made. Figure C.
NOTE
B
EFORE DRILLING, BE SURE THAT NO PIPING OR ELECTRIC CABLES ARE INSIDE
THE WALL
.
5. Reassemble the side panel (B), fasten the screws (2 and 3).
6. Insert the screw anchors (4) in the holes, the screws (5) in the panel’s slots and screw
down. (Note: items 4 and 5 are not supplied) – see Figure C.
7. Reassemble the lid (A) and fasten the screws (1).
Figure A Figure B