Engineering Manual
7 Test Run
Supply approximately 1000cc of water to the air outlet.
*Through this test run, check that drainage is discharged properly and that there is no water leakage from any of the connections.
*Refer to the installation manual of the indoor unit together with this manual.
1. Supplying water
Water supply pump
Air outlet
2.Carrying out a test run
(1) Turn the power ON.
(2) Press the TEST RUN button on the remote controller twice.
(3) Press the MODE button to select cooling mode.
*The drain lift up mechanism will be activated to start discharging the water.
(4) Check whether water is discharged properly.
(5) Press the POWER ON/OFF button to cancel the test run.
(6) Turn the power OFF.
3.Re-install each part after checking.
*If the drain lift up mechanism is installed at the time of the year
when heating is used, make sure that the water for the drain check
has been removed.
After removal of the water, reinstall the drainage plug.
Drainage plug
Drain pan
Drain Pump PAC-SH84DM-E