Specifications

824
FDC-HKX
Drain test
[Perform this before installing the ornament panel]
Perform this upon completion of electrical work.
Gradually introduce 2,000~3,000cc of water as shown below.
If the electrical work has not been completed, connect a convex joint
in the drain pipe connection to provide a water inlet.
Then, check if water leaks from the piping system and that drain flows
through the drain pipe normally.
Mounting the Panel
1 Open the inlet grille and remove the air block panel from the inside. (Remove the 2 screws.)
Drain piping connection port
Fill from outlet port
Pour water into a convex joint
Connect the remote control switch and set to cooling operation. The drain pump will operate with the compressor on.
Test whether or not the water is draining while listening to the operating sounds of the electric motor for the drain water.
Unit
Check the drainage condition by using the transparent socket.
Drain hose (provided)
Check that water is draining smoothly and that there is no water dripping from the connections or other areas.
Air block panel
()