Installation manual

- 8 -
6 Securely seal the cable lead-in port with putty to prevent dew, water and
insects, etc. from earthing.
* Seal the space between the electric box and conduit with putty.
7 Install it on the electric box.
8 Replace the surface cover.
M-NET transmission
cable
Type of the cable; Sheathed vinyl cords or cable which comply with the following specifications or
equivalent.
CPEVS φ1.2mm to φ1.6mm
CVVS 1.25mm² to 2mm² (AWG16 to 14)
* CPEVS; PE insulated PVC jacketed shielded communication cable
* CVVS; PVC insulated PVC jacketed shielded control cable
PE: Polyethylene PVC: Polyvinyl chloride
DC power cable The DC power cable should comply with both local standards as well as the power requirement of the
unit.
Recommended type: 0.75mm² to 2mm² (AWG18 to 14), 3-conductor power cable
Cable length: Within 50m (164 ft)
CAUTION
* Do not connect the AC power cable to the M-NET and POWER (24VDC) terminal blocks of the controller. It may cause a failure.
* The conduit outlet is only vertical facing. When leading the cable out from above, seal the port so that water does not enter
along the transmission cable and DC power supply cable.
Back of controller
M-NET
transmission
cable
DC power cable
* When using bridge wiring of the shield,
use the S-terminal as shown below.
M-NET transmission cable
DC power cable
Conduit
Electric box
Seal with putty
Bushing
M-NET transmission cable
or DC power cable
Wall
Lock nut
Installation plate A type
M4 flathead screw
M4 rounded screw
NOTE
* If the screw provided for the installation plate,
cannot be used because of the wall thickness, use
an M4 flathead screw that matches the wall
thickness.
* When using an LAN and external signal I/O, refer to
section 11 External input/output usage .