Specifications

Draper Prison Wasatch & Oquirrh Intercom & Paging System Remodel 4-21-2014
CONDUCTORS AND CABLES 260120 – 6
2. Electrical Tests:
a. Perform insulation resistance test on each conductors for feeders 100 amps and
greater with respect to ground and adjacent conductors. Applied potential shall
be 1000 volts dc for 1 minute.
b. Perform continuity test to insure proper cable connection.
3. Test Values:
a. Minimum insulation resistance values shall not be less than two megaohms.
B. Test Reports: Prepare a written report and submit to the Electrical Engineer at the completion
of the project. The report shall include the following:
1. Test procedures used.
2. Test results that comply with requirements.
3. Test results that do not comply with requirements and corrective action taken to achieve
compliance with requirements.
END OF SECTION 260120