ELECTRICAL DEMOLITION 260080 – 2
C. Maintain circuit integrity and continuity of all existing circuits/feeders, and systems that interfere
with or are interrupted by remodel work, unless those circuits/feeders are to be abandoned
completely. Maintain all circuits and systems in operation during construction. Provide
temporary panels, temporary wiring and conduits, etc. as required.
D. Leave all existing fixtures, devices, equipment, etc. In portions of the building not being
remodeled, in working condition.
E. Remove and dispose of all raceways, conductors, boxes, devices, equipment, etc., that are not
to be reused. Terminate at accessible junction box by providing proper knockout closure, tape
conductors, and label as "spare" with circuit no., Zone no., or other characteristic identifying
source.
F. Existing raceways may be reused, if in place, where in compliance with the contract documents
and the National Electrical Code. Upgrade and/or provide new conduit supports where
necessary for all raceways being reused. Insure integrity of existing raceways before re-use.
G. Return to owner all light fixtures which are to be removed. Dispose of all light fixtures if so
directed by owner in accordance with local environmental laws and policies. Those fixtures
indicated for re-use shall be thoroughly cleaned, repaired as required, re-lamped, and installed
as indicated. When storing fixtures for reuse, store in area and/or provide protective covering
that will keep construction dust and materials off fixtures.
H. Completely remove all telephone or data cables which are to be removed back to source or as
directed by owner.
I. Disconnect and remove all sound system equipment including speakers, amplifiers, etc. And
return to owner. Completely remove and dispose of all associated conduit and wire.
3.3 PATCHING AND REPAIR:
A. Finished Surfaces: The electrical contractor is responsible for patching and repair of all
existing interior surfaces pertaining to the installation of work under this Division, unless
specifically noted elsewhere in the contract documents. Where patching and repair is
necessary, surfaces shall be finished (painted, etc.) to match the adjacent materials, finished,
and colors. Requirements of other Divisions such as Division 9 - finishes shall apply.
B. Hard Surfaces: Whenever excavation or trenching is required for the installation of electrical
work, it shall be the responsibly of the electrical contractor to make repairs and/or replacements
of hard finish surfaces such as concrete, asphalt, etc. Requirements of other Divisions such as
Division 2 – Existing Conditions shall apply.
3.4 CONCEALING:
A. All raceways shall be concealed within the ceilings, walls, and floors, except in locations where
exposed raceways are specifically permitted, such as equipment rooms and unfinished storage
areas.
B. Surface-mounted raceways or systems shall be permitted only where approved by
Architect/Engineer.
END OF SECTION 260080