Specifications
Draper Prison Wasatch & Oquirrh Intercom & Paging System Remodel 4-21-2014
ELECTRICAL GENERAL PROVISIONS 260001 – 4
B. Certify the "Red Lined Drawings" for correctness. Indicate on each drawing the name of the
general and electrical contractors with signatures of each representative responsible for the
work.
C. The electrical engineering design firm will create record (as-built) drawings from the certified
red-lined drawings; however, the general and electrical contractors retain the responsibility for
the accuracy of the
1.10 WARRANTY:
A. Ensure that the electrical system installed under this contract is in proper working order and in
compliance with drawings, specifications, and/or authorized changes and is free from electrical
defects. Without additional charge, replace or repair, to satisfaction of the owner's
representative, except from ordinary wear and tear, any part of the installation which may fail or
be determined unacceptable within a period of one (1) year after final acceptance or as
otherwise indicated in individual sections, but in no case less than one year. Warranty
incandescent and fluorescent lamps only for a period of two months from the date of substantial
completion.
B. Provide complete warranty information for each item including beginning of warranty period,
duration of warranty, names, addresses, and telephone numbers and procedures for filling a
claim and obtaining warranty services. Written warranties and guarantees are to be submitted
separately as:
1. Originals bound in a binder clearly identified with the title, “WARRANTIES AND
GUARANTEES,” the project name, the project number, and the Contractor’s business
name.
2. Electronic documents in *.pdf format.
PART 2 – PRODUCTS
2.1 GENERAL:
A. All materials shall be new and shall bear the manufacturer's name, trade name, and the
approved testing laboratory such as the UL label in every case where a standard has been
established for that particular material. Used materials are acceptable only if specifically
indicated on drawings.
2.2 SUBSTITUTION OF MATERIALS:
A. Provide only specified products or products approved by addendum. Substitutions will be
considered if two copies of the proposal is received at the architect's/engineer's office eight (8)
working days prior to the bid day. Include in the proposal the specified and proposed catalog
numbers of the equipment under consideration and a catalog cut sheet(s) with pictorial and
descriptive information. Certify that the equipment proposed is equal to that specified, that it
has the same electrical and physical characteristics, compatible dimensions, and meets the
functional intent of the contract documents.
B. It is the responsibility of the contractor to make all substituted equipment comply with the intent
of the contract documents and bear all cost associated with conflicts arising form the use of
substituted equipment.
C. Provide samples if so required by the architect or engineer before or after bid day.
Bid DA14027DFCM
5/30/2014 2:08 PM p. 60