Draper Prison Wasatch & Oquirrh Intercom & Paging System Remodel 4-21-2014
ELECTRICAL GENERAL PROVISIONS 260001 – 3
performed under this contract.
1.7 SUBMITTALS:
A. The contractor shall submit complete shop drawings and other required submittals. Incomplete
submittals will be returned to the contractor unreviewed. No time extensions or cost increases
will be allowed for delays caused by the return of incomplete submittals.
B. Shop Drawings: After the contract is awarded, but prior to manufacture or installation of any
equipment, submit eight (8) complete sets of shop drawings. Partially complete sets of shop
drawings are not acceptable. Submit all shop drawings in one complete submittal package.
Prior to submitting shop drawings, review and certify that they are in compliance with the
contract documents; Sign all approved shop drawings. Allow a minimum of two weeks for
architect/engineer to review shop drawings. Refer to architectural general provision section for
additional requirements.
C. Provide equipment catalog “cut sheets”, brochures and/or drawings which clearly describe the
proposed equipment. Include plans, elevations, sections, isometrics, and detailed engineering
and dimensional information as applicable including equipment room layouts. Electrical room
layouts are required to show all electrical equipment locations for all projects that include
electrical rooms. Do not submit catalog sheets which describe several different items in
addition to those items to be used, unless all relevant information is clearly identified. Bind each
information set in three ring binder or binders of sufficient size or sizes to enclose all
information. Organize all information by section. Provide separate tabbed covers for each
section of Divisions 26, 27, and 28, indicating section number for each section requiring
submittals.
D. Include on front cover of binder or binders the name and location of the project, architect,
electrical engineer, general contractor, electrical contractor, subcontractors, supplier/vendor,
order number, volume, date, and any other applicable information. Certify that shop drawings
are submitted in accordance with the contract documents with a written statement indicating
compliance. Submittals will be reviewed and comments produced two times maximum.
Additional reviews will be billed at current rates.
1.8 OPERATION AND MAINTENANCE MANUALS:
A. Submit four (4) complete sets of operating instruction and maintenance manuals for all
equipment and materials provided under Divisions 26, 27, and 28.
B. Provide manufacturer's recommended operating and maintenance instructions, cleaning and
servicing requirements, serial and model number of each piece of equipment, complete list of
replacement parts, performance curves and data, wiring diagrams, warranties, and vendor's
name, address, and phone numbers. Do not submit information which describes several
different items in addition to those items to be used, unless all relevant information is clearly
identified. Assemble all data in completely indexed volume or volumes. Engrave the job title,
and name, address, and phone numbers of the contractor on the front cover and on the spine.
Incomplete O&M manuals will be returned to the contractor for corrections / additions.
1.9 RECORD DRAWINGS:
A. Maintain on a daily basis a complete set of "Red-Lined Drawings", reflecting an accurate record
of all work including addendums, revisions, and changes. Indicate precise dimensioned
locations of all concealed work and equipment, including concealed or embedded conduit,
junction boxes, etc. Record all "Red-Lined Drawing" information on a set of full sized prints of
the contract drawings.