User`s manual

11
6. To test the UPS turn OFF commercial power by either turning OFF the breaker supplying power
to the commercial receptacle, or using a switchable power strip.
7. Due to physical stability requirement for CP3K/2 series, please install the supporter to the UPS at
the bottom side with two screws.
8. External battery pack installation for CP2K/2 and CP3K/2
Remove the top lid from both units.
Remove the side panel (left side for CP3K/2, two sides for CP2K/2) from the control unit,
and the right side panel from the battery pack.
Connect the cable (CP3K/2: Anderson connector, CP2K/2: Fastons connector to the
power stage connector marked CN15) at the control unit. Then connect Anderson
connector to the battery pack.
Slide the units together, so that bracket "A" lines up on the left side of the control unit and
on the right side of the battery pack.
Install both top lids with screws again.
Install two brackets labeled "B" between the two units at the back.
The UPS is now ready for normal start-up and check out.