4.3.3 Power-on check
The ICT Cabinet must be connected to the system network before a power-on check
can be completed.
Ensure all the circuit breakers are up and providing power to the devices.
Check the status of the power LED and Ethernet link LEDS on the Cisco Switch in Figure 11 below
to
confirm the unit is working correctly. The SFP (if using fibre) should have a flashing green light when
data present and each Ethernet port with an active device connected will also have a green flashing
light.
If the SFP port doesn’t have an active green light there may be an issue with the fibre connection
back to the network. If the connected Ethernet ports don’t have an active green light and the
Ethernet cables have tested positive, then there may be a fault with the ICT cabinet.
Figure 11 Cisco Switch