Installation Guide

Wi-Fi WASP Infrastructure Installation Guide
Installation Guide
Section 4 Installing Infrastructure
Rev: 1 18 / 28
© Minetec 2019
Table 4 Bridge LED states
LED LED activity Description (default behaviour, all voltages nominal)
Network
Solid green Device has joined a network.
Off
Device has not joined a network. Confirm Power LED OK. Bridge fault if Access
Point network is available and in range for wireless connection.
System
Flashing green
Device OK. The flash cycle frequency changes during start-up and with data
load.
Off Device fault if Power LED is solid green (‘Voltage OK’). Confirm Power LED OK.
Power
Solid green Voltage OK.
Solid orange Under voltage (10 Vdc < V
IN
< 12 Vdc). Check power supply.
Solid red Over voltage (57 Vdc < V
IN
< 60 Vdc). Check power supply.
Off Invalid input voltage (V
IN
<10 Vdc or V
IN
> 60 Vdc). Check power supply.
4.3 ICT Cabinet
The ICT Cabinet (Figure 10 on page 19) converts long range power (240Vac) and network (fibre) to
short range power (24Vdc) and network (Ethernet). The mounting options for ICT Cabinet are:
Wall mount.
Hanging frame with chain and eye bolts.
Custom made stand.
4.3.1 Before you start
Before commencing work, plan and prepare for the installation ensuring that you read, understand
and perform the appropriate planning and preparation steps including, but not limited to:
Guidelines on page 4
.
Planning on page 7.
All electrical work to be done by qualified, authorised and deemed competent persons.
The work area is clear and free from hazards.
All relevant onsite permissions and permits to work have been obtained.
All safety precautions are in line with Mine Operator policy.
All required hardware and cabling is available.
Before going underground, complete the following preparation on the cabinet:
If using a hanging frame, attach the ICT Cabinet to the frame, making sure all bolts are secure.
If mounting to a threaded rod, attach the reo bar to the top and bottom of the ICT Cabinet.
Ensure the correctly sized and placed holes have been drilled in the reo bar.
Ensure the location meets the following criteria:
o Fibre and 240Vac power in close proximity.
o Device/s to be supplied are in close proximity.
o Greater that 600mm from any high voltage cables.
Prepare the power and Ethernet cables: