Installation Guide
Table Of Contents
Wi-Fi WASP Infrastructure Installation Guide
Installation Guide
Section 4 Installing Infrastructure
Rev: 1 12 / 28
© Minetec 2019
Step
Action/Response
Comments
When ready, complete a basic power-
on check.
page 12 for expected LED states
when connected to power.
8) Mark up.
Mark up (red line) installation drawings
to indicate any changes to installation
locations (cabling or AP).
Installation of the device is now
complete.
4.1.3 AP power-on check
A short time after the power is turned on, each of the LEDs should display Normal operations at
indicated in Table 3 below
. Abnormal operation LED states are also detailed.
Table 3 AP LED states
LED LED activity Description (default behaviour, all voltages nominal)
Network
Solid green Wireless network available to devices.
Off
Wireless network unavailable (eg reconfiguring network or fault).
Confirm Power LED OK.
System
Flashing green
Device OK.
The flash cycle frequency changes during start-up and with data load.
Off
Device fault if Power LED is solid green (‘Voltage OK’).
Confirm Power LED OK.
Power
Solid green Voltage OK, 12 Vdc <= Vin <= 55 Vdc
Off Extreme low input voltage (V
IN
<6 Vdc). Check power supply.
Solid orange Under voltage (6 Vdc < V
IN
< 12 Vdc). Check power supply.
Solid red Over voltage (55 Vdc < V
IN
). Check power supply.