Installation Instructions

When all your pavers are cut and in place, put a piece
of 3/4" plywood down and vibrate on top of that to help
distribute the weight of the machine, vibrate the
entire patio on low setting, starting at the outer edge
and working inward in a circular motion (Image 13). The
vibrator will lock the pavers into the sand and help even up
the surface. Don’t
let the vibrator sit in one place too long, or pavers could
settle unevenly or crack.
If a paver sinks deeper than its neighbors, use a
screwdriver to pry it up, sprinkle a little extra sand in the
void, then replace the paver.
Tamp the patio with a flat-plate vibrator,
on top of plywood, after all the pavers are
installed. Tamp entire outside edge first,
then circle in.
Sweep Paver Locking Sand into the paver
joints. Once paver surfaces have been
cleared, begin dampening paver joints.
Care and Maintenance
A properly cared for block project can last for generations with minimal maintenance.
Here are a few tips to get the longest life out of your project:
• Cleaners and Efflorescence removers can clean off any dust, dirt, or efflorescence
that can build up during the installation of your project.
• Sealers beautify and protect your concrete and masonry surfaces as well as making
the colors richer.
• Do not use salt on your block project. Use of salt may severely damage your blocks.
• Avoid using fertilizers with Ammonium Sulfate on or around blocks.
Paver Locking Sand
Using a broom sweep Paver Locking Sand to fill the
paver joints. The joints should be filled to the paver
chamfer (shoulder). Compact sand into joint spaces
as thoroughly as possible. The use of a small plate
vibrator for compaction and a piece of plywood is
recommended. Carefully remove any remaining sand
from paver surface prior to dampening. The best
appearance is achieved by eliminating all sand from
the surfaces of the pavers. It may help to use a leaf
blower to remove all sand and dust from the top of
the paver and dust that might have settled before
watering.
Then use a garden hose with a fine misting nozzle
to dampen the filled joints. Do not over water the
joints and avoid letting water pool on the joints; a
light misting will achieve the best results. Repeat
dampening process three more times every 15-20
minutes. Allow the locking sand to dry undisturbed
for a minimum of 24 hours before allowing foot traffic,
and wait 48 hours for vehicle traffic. Humid and wet
conditions or low temperature will delay hardening.