5.1.5 Pedestal Installation of F-frames
The F-frame frequency converters are shipped with a
pedestal. The F-frame pedestals use 8 bolts instead of 4, as
shown in Illustration 5.29.
130BX472.11
Illustration 5.29 Pedestal Bolt Installation
To install a pedestal-mounted F-frame unit, perform the
following steps:
1. If using a kit to direct the airflow from the heat
sink to the outside vent on the back of the
frequency converter, verify there is a minimum of
100 mm ceiling clearance.
2. Install each M8x60 mm bolt with lock washer and
flat washer through the frame into the threaded
hole in the base. Install 4 bolts per cabinet. Refer
to Illustration 5.30
3. Install each M10x30 mm bolt with captive lock
washer and flat washer through the base plate
and into the threaded hole in the base. Install 4
bolts per cabinet. Refer to Illustration 5.30
130BX471.11
1
2
Illustration 5.30 Fastener Location Detail
1 M8x60 mm bolt
2 M10x30 mm bolt
Table 5.24 Legend to Illustration 5.30
5.1.6 Lifting
Lift the frequency converter using the dedicated lifting
eyes. For all E2 (IP00) enclosures, use a bar to avoid
bending the lifting holes of the frequency converter.
The following illustrations demonstrate the recommended
lifting methods for the different frame sizes. In addition to
Illustration 5.33, Illustration 5.34, and Illustration 5.35, a
spreader bar is an acceptable way to lift the F-frame.
WARNING
The lifting bar must be able to handle the weight of the
frequency converter. See 5.1.1 Mechanical Dimensions for
the weight of each frame size. Maximum diameter for
the bar is 2.5 cm (1 inch). The angle from the top of the
drive to the lifting cable should be 60
°
or greater.
How to Install VLT® HVAC Drive FC 102 Design Guide
MG16C102 - Rev. 2013-08-20 97
5