Operating instructions

10

DFX & DBX Series Vent Free Fireplaces

If unit is to be “built in”, replace framing can be built before
or after the appliance is set in place. 

   
Construct replace framing following
 for replace dimensions. The framing
headers may rest directly on top of the rebox.
The replace may be installed directly on a combustible
oor or a raised platform of an appropriate height. Do
not place replace on carpeting, vinyl, tile or other soft
oor coverings. It may, however, be placed on at wood,
plywood, particle board or other hard surfaces. Be sure
replace rests on a solid continuous oor or platform with
appropriate framing for support and so that no cold air can
enter from under the rebox.
Anchor replace to the side framing members using nail-
ing anges.
   
J 6C\v" 6C\v" 31Z\v"
(680 mm) (680 mm) (800 mm)
K 5" 5" 3ZC\zn"
(635 mm) (635 mm) (833 mm)
FP445
Figure 6 -
Custom Cabinet
When finishing a custom cabinet, mantel or other built-in
enclosure, the opening size to accommodate the replace with
trim installed is as follows:

   
 

1. Bend out the nailing anges located on each side of the
rebox.
. Slide the rebox into prepared framing or position rebox
in its nal position and frame later.
3. Level the rebox by checking the top edge of the rebox.
Shim if necessary.
4. Anchor rebox to the side framing members using 8d
nails or other suitable fasteners. 
5. The canopy must be installed for safe operation of
the heater.    for canopy installation
details.
FP2509
nailing flanges
Nail Sides
Through Nailing
Flanges
FP509
Figure 7 -
Nailing Flanges