Network Card User Manual
Table Of Contents
- MGE Network Solution
- Installation and Configuration
- Supervision / Administration via a Web browser
- Servers protection
- Set-up of the shutdown parameters
- The different server and UPS shutdown sequences
- Configuring a set of cards with Mupgrade
- Configuration in local mode and via Telnet or SSH
- Maintenance
- Appendices

www.mgeups.com
Network
Management Cards
User Manual
THE UNINTERRUPTIBLE POWER PROVIDER
Network Management Card
– User Manual 34003676EN/GA
Page
47/69
4.1.4.1 Load shedding or sequential shutdown
It is possible to optimise backup time by shutting down non-priority equipment or sequencing the shutdown of
several devices.
Two shutdown criteria are possible:
Shutdown of outlets after a set battery back-up time (ShutOff Delay)
Shutdown of outlets at a given battery discharge level (ShutOff Level)
It is possible to specify values for both criteria. The first criterion reached will initiate server shutdown.
4.1.4.2 Sequential startup
It is possible to delay outlet power-on to reduce inrush currents on startup or to sequence the startup of several
devices.
Outlet startup after a given time is based on startup of the main outlet (Restart delay)