Specifications

METTLER TOLEDO Weigh Module Systems Handbook
(12/99)9-6
For a Structural Beam Foundation:
Use through bolts, washers, and nuts to anchor the base plate to the flange of the
structural beam (see Figure 9-6). Install web stiffeners to prevent the beam from
twisting. If shimming is required to level the base plates or to keep them in the same
plane, add the shim beneath the entire base plate. For bolting the base plates, use four
M10 or 3/8-16 UNC anchor bolts. For welding the base plates to the beam, use a 3-
inch fillet, 1 inch long on 3-inch centers.
Base Plate
Hex Bolt
Flat Washer
Flat Washer
Lock Washer
Hex Nut
Web Stiffener
Figure 9-6: Base Plate Bolted to Structural Beam
6.
After securing all the top plates and base plates, slowly back out the nut and
centering washer on each hold-down bolt, carefully lowering the top plate and
weigh structure onto the load cells.
7.
After all the top plates are down and applying load to the load cells, make sure
there is adequate clearance between the hold-down bolts and retaining holes. See
Figure 9-7 and Figure 9-8.
Figure 9-7: Hold-Down Bolt Assembly
Hold-Down
Top Plate
Base Plate