Specifications
Chapter 11: Tension Weigh Modules
Installation
(12/99) 11-3
Installation
To maintain the system’s weighing accuracy, make sure that the support steel will not
deflect more than 1/16 inch under full working load.
General Procedure
1.
Position the tension weigh modules around the tank so that each will support an
equal portion of the tank’s weight (see Figure 11-2). Make sure that the upper and
lower support brackets line up with these positions.
120
º
120
º
120
º
90
º
90
º
90
º
90
º
Figure 11-2: Plan View of Recommended Weigh Module Arrangements
2.
Connect each weigh module clevis to an appropriately sized threaded rod with a
jam nut on it. See Table 11-1 for clevis thread sizes. Tighten the jam nut against the
clevis to prevent the threaded rod from turning.
0978 Weigh Module Capacity Clevis Thread Size
50 to 300 lb 3/8 inch - 16 UNC
500 to 3,000 lb 3/4 inch - 10 UNC
5,000 to 10,000 lb 1 inch - 8 UNC
25 to 100 kg M8 x 1.25
200 to 1,000 kg M12 x 1.75
2,000 to 5,000 kg M24 x 2
Table 11-1: Clevis Thread Sizes
WARNING
USE SAFETY CHAINS OR RODS TO PREVENT TANK FROM FALLING IN CASE OF
COMPONENT FAILURE.