Resistance to earth connection and equipotential bonding measurement procedure
Select continuity function (RLOW or CONT) using the BACK / NEXT keys of
function selector.
Set sub-function to RLOW.
Enable and set limit (optional).
Connect test lead to the top of the instrument.
Compensate the test leads resistance (if necessary, see section 5.2.3).
Disconnect from mains supply and discharge installation to be tested.
Connect the test leads to the appropriate PE wiring (see Figure 5.12).
Press the TEST key to perform the measurement.
After the measurement is finished store the result by pressing the MEM button
(optional).
Figure 5.13: Example of RLOW result
Displayed result:
Main RLOW resistance.
Sub results checking
Press the key TAB for a few seconds.
The instrument will display sub result r1.
Click the key TAB.
The instrument will display sub result r2.
Next click on the key TAB will return the instrument to display main result.
5.2.2 Continuous 7 mA resistance measurement CONT
In general, this function serves as standard Ω-meter with a low testing current. The
measurement is performed continuously without polarity reversal. The function can also be
applied for testing continuity of inductive components.