46     Service Manual SM-MDS_(i) 
5.1 Obtain Design Drawing and Report 
During the design of MDS system by using the selection software, the user will draw the equipment layout on the 
software workplace. After completed the drawing, the software will select the appropriate outdoor model base on 
the user requirement. Once all this is completed, user will be able to generate the report. The system layout and 
report is necessary in order to have a smooth running commissioning process. 
5.2 Check Piping Routing, Wiring Routing & Connection 
After obtaining the design drawing and report, we will need to check on the piping and wiring connection. 
Although this should be done during installation, it is better to check all items again before commissioning. 
Piping 
Routing 
Ensure both liquid and gas pipe are insulated according to the specification stated below. For hot 
and wet environment, it is recommended to increase the insulation thickness. If there is special 
request due to customer requirement or country regulation, please follow the specification stated. 
 Pipe Specifications 
Diameter (mm)  6.25 to 25.4  28.58 to 41.3 
Thickness 
At least 
10mm 
At least 
12mm 
Heat insulation  At least 100ÂșC 
EXV Box 
Ensure that the orientation of the EXV box is in vertical condition. 