c)  Ensure that the compressor is not expose to open air for more than the recommended time specified by 
its manufacturer (typically less than 10 minutes). Removed the seal-plugs only when the compressor is 
about to be brazed. 
d)  The system should be thoroughly vacuumed to 1.0 Pa (-700mmHg) or lower. This vacuuming level is 
more stringent than R22 system so as to ensure no incompressible gas and moisture in the system. 
e)  When charging R407C, ensure that only liquid is being withdrawn from the cylinder or can. This is to 
ensure that only the original composition of R407C is being delivered into the system. The liquid 
composition can be different from the vapor composition. 
33% / 33% / 34% 
23% / 25% / 52% 
R32/R125/R134
Composition of R407C in vapour phase 
is different from liquid phase. 
f)  Normally, the R407C cylinder or can is being equipped with a dip-pipe for liquid withdrawal. However, if 
the dip-pipe is not available, invert the cylinder or can so as to withdraw liquid from the valve at the 
bottom. 
Liquid 
withdrawal 
Invert cylinder 
without dip-pipe 
Dip-pipe 
g)   When servicing leak, the top-up method, commonly practiced for R22 system, is not recommended for 
R407C system. Unlike R22 where the refrigerant is of a single component, the composition of R407C, 
which made-up of three different components, may have changed during the leak. Consequently, a 
top-up may not ensure that the R407C in the system is of original composition. This composition shift 
may adversely affect the system performance. It is recommended that the system should be evacuated 
thoroughly before recharging with R407C. 