Specifications

Cat 604-3 39
Engineering Guide Specifications
chiller shall meet a minimum seismic design spectral
response acceleration of 1.60 SDS. The chiller must be
mounted to a rigid base and may use neoprene waffle
vibration pads.
6 Certified performance test in accordance with procedures
and to the tolerances contained in AHRI Standard 550/
590.
-- OR --
6 Witness performance test in accordance with procedures
and to the tolerances contained in AHRI Standard 550/
590.
PART 3 - EXECUTION
3.1 INSTALLATION
A installing contractor to:
1 Install per manufacturer's requirements, shop drawings,
and contract documents.
2 Adjust chiller alignment on foundations, or subbases as
called for on drawings.
3 Arrange piping to allow for dismantling to permit head
removal and tube cleaning.
4 Coordinate electrical installation with electrical
contractor.
5 Coordinate controls with control contractor.
6 Provide all material required for a fully operational and
functional chiller.
3.2 START-UP
A Factory Start-Up Services: Provide for as long a time as is
necessary to ensure proper operation of the unit, but in no
case for less than two full working days. During the period
of start-up, the start-up technician shall instruct the owner's
representative in proper care and operation of the unit.