TYPE I ... McQuay provides ease of installation without requiring construction alterations of
entryways to your building. The compressor and compressor control box are removed and put on
a skid. All associated wiring and piping will remain attached if possible. The remaining loose
parts will be packaged in a separate crate.
A. Blockoffs will cover all openings on the compressor and vessels.
B. The compressor and vessels will receive a nitrogen holding charge.
C. The compressor will not be insulated at the factory. An insulation kit will be shipped with the unit.
D. The starter will ship loose. Bracket and cable kit to be included for unit-mounted starters and/or
cableway for mini-cabinet.
E. The evaporator will be insulated at the factory.
F. Refrigerant will not be shipped with the unit and must secured locally and furnished and installed by
the installer.
G. Oil will be shipped in containers from the factory for field installation.
H. All field-piping connections will be victaulic, o-ring face seal or copper brazing.
I. All free piping ends will be capped.
J. Touch-up paint will be included.
K. The unit will undergo the rigorous, full McQuay test program at the factory.
TYPE II ... For those really tight installations, McQuay provides a total knockdown of the unit,
allowing entry to the chiller site using already existing entryways. Compressor and terminal box
are removed and put on a skid. The condenser, evaporator, and oil pump and supports will remain
connected only by the attachment bolts for easy disassembly at the job site or riggers. All wiring
and piping that interconnects the components will be removed. The remaining loose parts will be
packaged in a separate crate.
A. Blockoffs will cover all openings on the compressor and vessels.
B. The compressor and vessels will receive a nitrogen holding charge.
C. The compressor will not be insulated at the factory. An insulation kit will be shipped with the
unit.
D. Only the evaporator shell will be factory insulated. Loose insulation will be shipped for the
remaining surface areas.
E. The starter will ship loose. Bracket and cable kit to be included for all unit-mounted starters
and/or cableway for mini-cabinet.
F. Refrigerant will be field supplied.
G. All field piping connections will be victaulic, o-ring face seal or copper brazing.
H. All free piping ends will be capped.
I. Touch-up paint will be included.
J. A bolted bracket instead of a weld will mount the oil pump.
K. The discharge piping assembly will have a bolted flange connection at the condenser. This
assembly will be shipped loose.
L. Piping that is attached to a component will be supported if it is not rigid.
M. All pressure vessels receive the full ASME testing. The compressor and oil pump are pressure
checked and run tested. The chiller will require field leak testing after assembly at its final
location.