Install Instructions

5
STEP 2 - Determine the Location of the Flow Switch
a. The flow switch must be installed in the pipe using
a threaded tee connection or welded fitting of
minimum length such as a half coupling. Use a
face or hex bushing to reduce the tee outlet to 1"
(25mm) pipe thread if a reduced tee outlet thread
size fitting is not available.
The flow switch should be located in a horizontal
section of pipe where there is a straight horizontal run
of at least 5 pipe diameters on each side of the flow
switch. The flow switch may be installed in a vertical
pipe if the flow is in the upward direction.
The flow switch must be installed in the upright
position as shown with arrow mark on side of casting
in the same direction as fluid will flow.
Some system conditions that require more than 5 pipe
diameters are high viscosity fluid and high fluid velocity.
The flow switch must be installed in the pump suction
piping when spring-loaded check valves and/or other
close coupled accessories are installed in the pump
discharge piping.
1" (25mm)
1"
(25mm)
1"
(25mm)
Threaded
Pipe
Threaded
Pipe
Threaded
Pipe
Welded
Pipe
b. When installing in brazed/soldered copper pipe,
size the threaded adapter to ensure the paddle
arm extends into the main run of the pipe
STEP 3 - Connecting the Flow Switch to Pipe
FLOW
a. Insert the 8/32 x 1/4" flathead screw through
washer and paddle. Attach screw to opposite side
of the paddle arm’s curve and tighten to a torque
of approximately 12-16 lbin (1.36-1.81 Nm).
NOTE: If two paddles are being installed, they
must be stacked one on top of the other with the
longer paddle first in line to the flow.
CORRECT
INCORRECT