Installation Tasks
2-11
Installation Tasks
NOTE: The director does not have a power switch. Therefore the director
powers on when its power cords are connected to facility or rack power.
Figure 2-3 AC Power Connections (Director)
9. Connect the equipment rack power cords to separate (for
redundancy)facilitypower sourcesthatprovidesingle-phase, 180
to 264 VAC voltage.
10. Power on the rack power strips.
11. Inspect the front panel of each rack-mounted Ethernet hub.
Ensure each green Power LED illuminates.
12. The director powers on and performs POSTs. During POSTs:
Amber LEDs on both CTP cards and all port cards illuminate
momentarily.
The green LED on each CTP card (active and backup) and
each port card illuminate as the card is tested.
Green LEDs associated with Fibre Channel ports sequentially
illuminateastheportsaretested.
13. After successful POST completion
Bezel: POWER LED green
Active CTP card: LED green
Power supplies: PWR OK LEDs green
14. If a POST error or other malfunction occurs, go to Chapter 3,
MaintenanceAnalysisProcedures(MAPS)to isolate the problem.
15. Perform one of the following: