Service manual

2
Installation Tasks
2-9
Installation Tasks
c. As shown in use a pointed instrument to set the
medium-dependent interface (MDI) switch on the top and
middle hubs to MDI (in) (Figure 2-1, 1 and 2). Set the MDI
switch on the bottom hub to MDIX (out) (Figure 2-1, 3).
NOTE: To connect two hubs, follow step b and step c (middle and
bottom hub) instructions.
6. Connect a power cord to a rack power strip and the receptacle at
the rear of each hub. Power for each hub switches on when the
hub (and equipment rack) are connected to facility AC power.
NOTE: Ensure each hub is connected to a separate rack power strip.
7. Inspect the front panel of each hub. Ensure each green Power
LED illuminates.
Task 3: Unpack, Inspect, and Install the Director
The following paragraphs provide instructions to unpack, inspect,
and install the director in a rack-mount configuration. If the director
is deliveredin a Fabricenter equipment cabinet,go to Ta sk 5: Co nf igu re
Director Network Information (Optional) on page 2-30.
CAUTION
Use safe lifting practices when moving the product.
Unpack and inspect the director.
1. Inspect shipping containers for damage. If a container is
damaged, ensure a freight carrier representative is present when
the container is opened. Unpack shipping container(s) and
inspect each item for damage. Ensurepackaged items correspond
to items listed on the bill of materials.
2. If items are damaged or missing, contact the solution center:
Phone: (800) 752-4572 or (720) 558-3910
Fax: (720) 558-3851
E-mail: support@mcdata.com