Factory Testing can include, but is not limited to:
Functional test of full parallel RPA system including transfers
to bypass, utility failure, EPO etc.
Full Functional test of parallel RPA system including master
fail and communications failure simulations
Steady state measurements from 0-100% load of voltage,
current, output voltage regulation, input/output power
factor, output voltage THD, input current THD, frequency.
Overload of full system up to 150%
100% utility failure with waveform capture
Factory Testing and Customer Witness Testing
0-100% step loads with waveform capture
0-100% bypass transfers with waveform captures
Output short circuit with waveform capture
Removal of module from the system with waveform capture
Inverter or power supply failure simulations
Full functional test of RPA output switchgear including
transfers in and out of main bypass mode
Field Testing & Service Capabilities
On-Site Services that include:
UPS Module Startup & Test
Battery Measurement & Monitoring
Load Bank Testing
Thermography Testing
Project Management
Site Commissioning Assistance
Repair, upgrade, retrot
Site Audits & Assessments