Before operating your lift, check to make sure both “A” and “B” measurements are equal. The lift arms must be level
before operation. If your lift arms are not level, shim the columns as required.
IMPORTANT LEVELING INSTRUCTIONS
7. Install both columns with bolts and washers to anchors, check plumb and measurements as shown below.
8. If shimming is required, insert the shims as necessary under the
base plate so that when the provided 5/8 x 2" anchor bolts are
tightened, the columns will be plumb both side to side and front to
rear. (See gure 15)
9. With the shims and anchor bolts in place, tighten all 5/8 x 2" anchor
bolts tight to the base plate. DO NOT USE AN IMPACT WRENCH or
the anchors could become compromised.
NOTE:
It will be helpful to mark on or otherwise note the location of shims
used at each drop anchor to assist at time of re-installation.
Inspect all drop-in anchors for proper setting and or damage each time the lift is re-installed. Inspect the concrete for
cracks defects and/or damage. Do not re-install the lift if any of the drop-in anchors are defective or the concrete is
cracked or defective.
It may be necessary to shim the columns to ensure that the columns are plumb. The columns must be plumb and
square or damage or injury may occur when using the lift. Do not exceed 1/8" total shim thickness.
Fig. 15