Installation Instructions

Table Of Contents
nanoLTE E61 AP Hardware Installation nanoLTE E61 AP Hardware Installation
NANO_INST_43325 v205_0.6 for N4G_2.5 © ip.access Limited 2019 Page 26
3) Mark the position of the four screw holes.
4) Drill the four holes in the positions marked previously and insert wall plugs (if
required) and fix the mounting bracket securely to the wall or ceiling.
5) Before fitting the AP onto the bracket, plug in the required cables. Plug the
Ethernet cables from a switch/gateway into the RJ45 sockets. If the Ethernet
cables do not carry PoE+, also plug the power supply into the +12V DC input. Also,
if required, connect a GPS source to the GPS port.
6) Position the E61 so that the rear lugs line up to the gaps on the side rails of the
bracket, then push the S62 AP onto the bracket and slide the AP until the retaining
spring engages the indent at the rear of the unit.