Installation Instructions
Table Of Contents
- nanoLTE E61 AP Hardware Installation
- Table of Contents
- 1 Introduction
- 2 Installation Overview and Requirements
- 3 nanoLTE E61 AP Commissioning
- 3.1 Requirements for Commissioning with the Web Page
- 3.2 Redirector First Contact and NTP Synchronisation for Software Update
- 3.3 Configure a Commissioning Terminal
- 3.4 Access the Commissioning Web Page for the LTE AP
- 3.5 Optional - Software Download
- 3.6 Configure the Connection to the NOS Server
- 3.7 Commissioning Complete
- 4 nanoLTE E61 AP Hardware Installation
- 5 Troubleshooting
- 6 AP and PSU Regulatory Information
nanoLTE E61 AP Hardware Installation nanoLTE E61 AP Hardware Installation
NANO_INST_43325 v205_0.6 for N4G_2.5 © ip.access Limited 2019 Page 25
4.3 Mount the E61 AP on a Wall or Ceiling
Note: The E61 AP should be installed in a position so that it is at least 2m away from the area
where handsets are normally used.
The location of each E61 AP should be shown on an installation floor plan produced at the
network planning stage. For example, it must take into account that all APs must be at least
2m from any mobile equipment. The network wiring must be complete before the E61 AP
can be installed. The E61 AP should be placed on a wall or ceiling at or above head height,
at a minimum height of 1.8m.
1) Remove the mounting bracket from the E61 AP. Lay the AP on a flat surface with
the mounting bracket upwards. Slide the removal tool over the central guide
groove over the fin between the bracket and the body of the unit to disengage the
locking spring, then slide the bracket to separate it from the AP. The removal tool
may be inserted from the top or bottom of the AP.
2) Position the bracket on the wall or ceiling with its flat side against the wall or
ceiling. For wall mounting, orient the clip part towards the top. Ensure the bracket
is level and sufficient clearance is maintained to allow the AP to be fitted to the
bracket.
For wall mounting, allow at least 100mm from the bracket to the top of wall, and
150mm from the side of the bracket to any side walls, as illustrated:
For ceiling mounted APs, allow 150mm clearance on all sides: