3.6.3 Configure the TR-069 Management Connection
3) Enter addresses for the NOS Server (or equivalent TR-069 ACS) in the ACS
Address field.
4) In the CRL Base Server URL, enter the URL for contacting a CRL mirror server.
Note: This is the "base URL" as the AP constructs a full URL of the CRL update
file to obtain on contacting the server.
5) In the NTP Server Addresses box, enter a comma separated list of the four valid
NTP server addresses that will be accessible to the AP via its backhaul network. If
the backhaul will use the Internet, these can be NTP servers on the public Internet.
Note: The NTP and CRL servers must be accessible to the AP on start up,
before it has established an IPsec tunnel to the IPsec Gateway.
Note: If the AP can connect to the Internet, the default "0.ipaccess.pool.ntp.org"
may only be used as an initial value. The final configuration of an
operational AP (as supplied from the NOS or other TR-069 ACS) must not
use the ip.access pool.
Note: To provide AP crystal discipline, the final configuration of the NTP servers
must comprise four stratum 1 time servers.
6) To save the configuration, click the Save button.
The settings applied on this page are retained permanently as the default set of
these parameters in the TR-196 data model, and can only be subsequently
changed on this web page from a commissioning terminal or from the Redirector
by assigning the AP to a different set of DOCP parameters.
Note: At this point it may be useful to make a note of the parameter values
entered in this screen. Alternatively, save a screenshot of the web page
(information about how to take a screenshot is outside the scope of this
manual).
3.6.4 Complete the LTE AP Commissioning
7) To start the LTE AP in normal operation mode, click Complete Commissioning.
8) Acknowledge the warning about changes in the IP configuration and click OK.
9) When the initial configuration is complete, power off the AP and disconnect it from
the commissioning terminal.
At this point, the commissioning web page is no longer accessible. If there are
configuration errors that prevent the AP connecting to its serving NOS Server, the
commissioning web page must be started again after resetting the AP with a
factory reset. See section 5.3 for factory reset instructions.