Installation Instructions
Table Of Contents
- nanoLTE E61 AP Hardware Installation
- Table of Contents
- 1 Introduction
- 2 Installation Overview and Requirements
- 3 nanoLTE E61 AP Commissioning
- 3.1 Requirements for Commissioning with the Web Page
- 3.2 Redirector First Contact and NTP Synchronisation for Software Update
- 3.3 Configure a Commissioning Terminal
- 3.4 Access the Commissioning Web Page for the LTE AP
- 3.5 Optional - Software Download
- 3.6 Configure the Connection to the NOS Server
- 3.7 Commissioning Complete
- 4 nanoLTE E61 AP Hardware Installation
- 5 Troubleshooting
- 6 AP and PSU Regulatory Information
nanoLTE E61 AP Hardware Installation nanoLTE E61 AP Commissioning
NANO_INST_43325 v205_0.6 for N4G_2.5 © ip.access Limited 2019 Page 12
3.1 Requirements for Commissioning with the Web Page
The following items are required for commissioning:
• A commissioning terminal, which can be either a desktop computer or a laptop,
with:
• OS: Windows® 7 or later
• Web browser: Microsoft Internet Explorer 7 or later
• JavaScript enabled in the web browser
• A spare connection to allow the AP to connect to the Internet - this is so that the AP
can connect to the Redirector briefly after a Factory Reset before switching the AP
over to the commissioning terminal
• A short Ethernet cable for connecting the commissioning terminal to the LTE AP
• A temporary means to provide power to the AP while it is connected to the
commissioning terminal - typically use the supplied power adaptor
• Optionally, if a software update is required, a copy of the required LTE AP software
file on the commissioning terminal - this should only be used if the LTE AP will not
be managed by the NOS, as there are additional requirements that must be met
when downloading software from an attached commissioning terminal
3.1.1 Information Required for Commissioning
Use this information to commission an LTE AP from the commissioning terminal, so that the
LTE AP can subsequently connect to its serving NOS Server.
It is possible to commission an AP before taking it on site.
For connecting to the LTE AP from the commissioning terminal:
• User name and password for the LTE AP’s web server - if necessary, contact
customer support at ip.access for the current user name and password
For commissioning the LTE AP:
• IP Address or FQDN of the serving NOS Server
• IP Address or FQDN of an NTP server
• DHCP or static IP
• If static IP is required:
• IP address for the LTE AP
•Netmask
• IP Address or FQDN of the default gateway
• IP Address or FQDN of the Primary DNS
• IPSec configuration (usually required, but see note below):
• IP Address or FQDN of the IPsec Gateway
• IP Address or FQDN of a CRL server