15.0 INSTALLATION CHECKLIST
Installation
Connect all plumbing, and ensure that there are no system leaks.
Connect, secure, and glue all vent piping.
Install all gas piping as per this manual, and local codes. Pressure test, to detect any gas leaks.
Start-up
Install pressure gauge (Gauge= 0” to 15” w.c. scale) and check line and manifold pressures. (See “Section 5.2”)
Turn gas shut-off valve to the ON position.
Turn Power on to boiler.
Set Sentry Controller to desired settings.
Turn thermostat up, Ignition will occur.
Operational Checklist
Ensure that Carbon Dioxide Readings are within the acceptable ranges. Using an appropriate Oxygen or Carbon Dioxide analyzer,
take a sample of the flue gas. The sample must fall within the acceptable Carbon Dioxide ranges, which is 8% - 9.5% for natural,
and 9.0%-10.5% for propane. (See Table 5.1)
Before Leaving
Remove gauge from gas valve and tighten bleed screw and test plug for leaks.
Allow boiler to complete at least one complete cycle, or at least 15 minutes running time.
Always verify proper operation after servicing