Technical data

CHAP-04.10 ELECTRICAL POWER DISTRIBUTION, DRIVES, CONTROL &
ILLUMINATION ELECTRICAL
Page 15 of 50
15. Cables of one area/conveying route will not cross and will not be laid
through conveyor of other area/conveying route.
16. Minimum 1 No. electrical area repair shop (Min. size 18M X9M X 6M)
in Coke Sorting Plant will be considered with a facility of rest room,
repair area, store, provision to keep tools and tackles, measuring
instruments/testing instrument including megger, clamp tester, hand
held tachometer, CRO, multimeter, vibrometer etc.
17. Furniture for the monitor, control rooms etc.
18. Training of EMPLOYER’s engineers at manufacturer's works/training
centers for Automation system, UPS system, AC drives, Weighing
system etc.
19. Any additional items/equipment which is necessary for achieving
specified performance and completeness of the system will be
provided by the Contractor within the time schedule unless it has been
excluded from the scope of the Contractor.
04.10.04. Approval of Statutory Authorities
The Contractor will obtain necessary approval of statutory authority as
per rules of State Government and Central Electricity Authority for the
work under his scope, before energizing/charging the equipment.
However, EMPLOYER will extend all assistance in this regard, like
submission of application, relevant documents and payment of statutory
fees etc.
04.10.05. Installation
For installation work at site, the contractor will be fully responsible for
arranging the required tools and tackles, welding sets, pipe bending
machine, cable crimping tools, gauges, scaffoldings, ladders, temporary
water and power connections.
On completion of the installation but before energisation of the system,
all installation will be physically checked and properly tested. These
checks and tests will be conducted by the contractor under the
supervision of BSP / MECON. The contractor will furnish the final status
and test results. Any defect observed during such check and tests will be
rectified by the contractor free of cost within contract completion period.
All clamps brackets, bolts, nuts, screws, markers, ferrules, lugs and
glands and other hardware necessary for erection work, will be included
in the scope of work and will be arranged by the contractor. Equipment
will be painted to withstand the heavily polluted and saline environment
prevailing in at site.