Technical data

CHAP-04.11 AUTOMATION
20. Power & Control Supply monitoring of all mechanisms will be provided
through PLC.
21. Status of UPS to be monitored through PLC / HMI.
22. All new PLCs supplied in this package, will be interfaced to Main PLC on
Ethernet. Apart from main PLC as described in automation configuration
drg., other PLCs (if) coming under this package shall interface with main
PLC of CHP/CSP/FFP
23. The communication networks will be dully tested & certified by
authorized agency.
24. For better co-ordination, the complete automation system will be ordered
on one sub-vendor i.e. the OEM of PLC system.
25. Ethernet network (FO and UTP)
GTS GS-12 shall be referred for specifications related to ethernet
network
FO link from CSP IV control room to main control room of
COB#11(Battery and CDCP) and from existing SP3 CR1 to main
control room of SP 3 machine 2 for exchange of needed information.
FO link to be used (Not UTP) if link taken outside building or shop
floor.
All FOC/UTP carrying conduits/pipes to be paint marked as per
standard color code specified by employer
04.11.02 SCOPE OF WORK AND SUPPLY
Contactor’s scope of work and supply will include design, engineering,
manufacture/ procurement, assembly, calibration, shop testing,
inspection at works & at site, painting, packing, transportation to site
including loading, unloading, storage & handling of all Automation
equipment including electrical accessories, cables, GI pipes, erection
accessories, panels/ cabinets and all associated hardware, as required
for completeness of Automation system in all respect along with site
fabrication, erection, testing, commissioning of the complete automation
system and interfacing with different PLCs as described else where in
the contract for completeness & satisfactory operation of the entire Coal
Handling Plant, Coke Sorting Plant and Augmentation in Flux - Fuel
Preparation and Plant Return Fines Handling for SP III as per
technological layout and material flow diagram. The scope of work will
also include liquidation of defect points, participation in tests for
establishment of plant performance guarantee (PG) and post
commissioning activities till issue of final acceptance certificate (FAC) by
BSP.