Now that all the hardware installation, cabling and labeling, and the powering
up steps are complete, you are ready to configure the DSSI subsystem and
verify the correct operation of each ISE in the array with the system.
Refer to the system installation manuals and TF857 Magazine Tape ISE
Service Manual (EK–TF857–SM) for detailed information and how to proceed
with verifying the correct operation of each ISE that has been installed. In
these manuals, you will find the procedure for establishing the communications
between the ISEs, the adapter module, and the system. You will also find the
step-by-step procedures for reconfiguring the system with its newly installed
DSSI devices.
Refer to the manuals for the disk ISE and tape ISE for detailed information on
the local programs in the ISEs.
Once the verification is complete, close the cabinet doors; turn the hex-Allen
fasteners one quarter turn clockwise to lock. The system is ready to be turned
over to the system manager.